|
ON-SITE SEWAGE SYSTEM INFORMATION
FOR: NEW CONSTRUCTION AND REPAIR OF EXISTING SYSTEMS
IN UPPER MILFORD TOWNSHIP
The
process of putting an On-lot Sewage Disposal System on a property is
as follows:
-
Call
the Upper Milford Township SEO (Sewage Enforcement Officer) at
(610) 966 - 3223 to set up an appointment.
-
At the
appointment, an application for an On-lot Sewage Disposal System
permit will be completed. After completing the application, the
fee structure will be explained. (Please have payment available
at this time.)
-
After
a completed application and payment have been received, the SEO
will instruct you to select where on your property you will want
to place your house (new only), well and sewage and disposal
system. You must obey the isolation distances below:
-
Minimum distances from septic tank(s), dosing tanks, pump
tank, filter tanks
-
10 feet from property line, easement or
right-of-way
-
10 feet from occupied buildings, swimming
pools, driveways
-
50 feet from wells or water supply
suction line
-
10 feet from water supply line under
pressure
-
25 feet from streams, lakes or other
surface water
-
25 feet from a cistern used as a water
supply
-
Minimum distances from absorption area
-
10 feet from property line, easement of
right-of-way
-
10 feet from occupied buildings, swimming
pools, driveways
-
100 feet from wells or water supply
suction line
-
10 feet from water supply line under
pressure
-
50 feet from streams, lakes or other
surface water, watercourses (wetlands are not surface
areas)
-
5 feet from other on-lot systems
-
10 feet from large rock formations
-
10 feet from any slope greater than 25%
-
25 feet from a cistern used as a water
supply
-
10 feet from detention basins, retention
basins, storm water seepage pits / areas Step
-
You
must then contract with someone with excavation equipment
(backhoe) to do test probes (minimum of two (2) needed per site
area).
-
The
backhoe operator MUST call PA One Call at (800) 242 – 1776 a
minimum of three (3) days prior to doing the excavation. The
serial number obtained should be called into the SEO when the
appointment for viewing the probes is made. The SEO can refuse
to schedule the probe viewing until this serial number is given,
and the minimum of three (3) days notification elapsed.
-
The
backhoe operator (or yourself) must call the Township SEO to
arrange for an appointment to meet at your property. The SEO
will instruct the backhoe operator to dig two (2) (or more)
seven (7) foot + deep trenches in the area(s) you desire your
sewage system. The soils will then be examined by the SEO. If
the soils are found to be suitable for an on-lot system, the SEO
will inform the property owner or your agent that you may
proceed to Step No. 7.
-
If
suitable soils are found, the SEO will ask that a percolation
test (s) be done within ten feet of the soil probe deemed to be
the most acceptable for on-site sewage disposal. The landowner
will then make arrangements for these tests to be conducted at
the specified area. The person conducting the testing is to
notify the SEO several days prior to the dates the test will be
run. This allows the SEO to witness all testing done or your may
choose to have the SEO run the test. Following the test, the
area tested is to be staked at the four (4) corners. NO FURTHER
TRAFFIC SHOULD BE ALLOWED ONTO THIS AND SURROUNDING AREAS.
-
The
SEO will calculate the results of the percolation testing along
with the results of the soil probes done previously. Written
documentation as to the suitability of the site tested to
support an on-site sewage system will be sent to the applicant.
-
If the
area is found to be acceptable for an on-site sewage system, the
landowner must then contract with appropriate parties to design
an appropriate sewage system. The designer should contact the
SEO for necessary information needed in designing the sewage
system.
-
The
completed design is then submitted to the SEO for review along
with permit review and issuance fee assigned by the Township.
Upon review, the design will be evaluated for accordance with
all regulations. If corrections or changes are necessary, the
designer will be asked to modify original submitted plans
accordingly. FOUR (4) COPIES OF PLANS ARE TO BE SUBMITTED FOR
REVIEW. If the submitted plans are in accordance with
regulations and correct, they will be approved for permit
issuance.
-
The
SEO will then issue a permit allowing the construction of the
on-site sewage system on the property which is valid for a
period of three (3) years from the date of issue. “A permit
shall expire if construction of installation of an individual
on-lot sewage system and structure for which the system is to be
installed has not begun within three (3) years after permit
issuance.” The permit (colored copy should be posted at site)
will be mailed to you with a single design copy with any
corrections or changes to the submitted design. It is important
that any changes be added to copies your designer may have given
you; also the contractor constructing the on-site system shall
have this updated copy to construct the sewage system off of!
-
When
the property owner decides to begin construction on his house /
sewage system, he is to contract the necessary parties to build
his sewage system. The person(s) building the system are to
contact the SEO several days prior to beginning construction on
the new system so that inspection dates may be arranged to view
construction progress at various times. NOTE: PLEASE SEE IMPORTANT
NOTES AT THE BOTTOM OF THIS PAGE.
-
When
the construction has started, the SEO will make periodic
inspections / tests at the site to confirm that the system is
being constructed according to all regulations, plans and that
isolation distances are being adhered to. These appointments are
arranged by the contractor constructing the sewage system.
-
When
the sewage system has been completed, the final inspection will
be made by the SEO to assure everything is operational. The
landowner’s copy of the application, along with percolation
results and other related information will be forwarded to the
owner for his files. (Please advise SEO of any changes in
address that may have occurred since the application was first
completed.)
The
Procedure is now complete
IMPORTANT NOTES:
1. Under
current regulations there are instances where land may not be able to support any on-site sewage system.
2.
IMPORTANT! Prior to any construction of house / sewage system, the
following shall be securely staked and marked.
ON-SITE SEPTIC TIPS:
|